Milling and Paving starting Tuesday, August 26th
The Jasper Street Department along with Calcar Paving will be milling the asphalt for the following streets, starting Tuesday, August 26th.
- Jackson Street from 3rd Street to River Centre Landing
- S. Newton Street between Church Ave. and Hochgesang Ave.
- 44th Street from US231 to Obing Strasse
Surface asphalt will be placed:
· S. Newton Street and 12th Avenue on Wednesday, August 27th
· Jackson Street and 44th Street on Thursday, August 28th
Motorists will experience delays if traveling these streets during construction. This schedule is subject to weather or unforeseen conditions.
Any questions, please contact Jasper Street Department 812-482-1130