12th Avenue Road Work UPDATE

July 31, 2019
The City of Jasper’s contractor, Knies Construction has completed Phase 1 of the 12th Ave reconstruction project & will open 12th Ave from US231 to Test Dr, for traffic, beginning at approximately 9:00 a.m. Thursday, Aug. 1.  Therefore, motorists will be able to access Uebelhor Toyota & SVBT’S ATM from US231.

Knies Construction will then begin Phase 2 of this project, thus closing 12th Ave from Test Dr to approximately 250 ft west of Power Dr.

Motorists wishing to access businesses west of this location, may do so by either using HRJ Ln & Kimball Blvd or Division Rd & St Charles St.

This schedule will proceed barring any unforeseen events or inclement weather.


Jasper Street Department
812-482-1130