UPDATE: Milling Work CANCELLED
UPDATED June 14, 2019:
The previously scheduled road work has been CANCELLED on the following streets, due to current & future building construction in this area.
- Wernsing Rd from Division Rd to the south end of Wernsing Rd
- 11th Ave from Wernsing Rd to the east end of 11th Ave
- Habig St from 11th Ave to the north end of Habig St.
---------------------------------------------------------------------------------------
The Jasper Street Dept along with contractor CalCar Paving, will begin Milling on Monday, June 17 at 7:00 A.M., on following streets:
- Wernsing Rd from Division Rd to the south end of Wernsing Rd
- 11th Ave from Wernsing Rd to the east end of 11th Ave
- Habig St from 11th Ave to the north end of Habig St.
Milling is expected to continue for 2 days, with Paving to follow the following 2 days. This schedule will remain in effect barring inclement weather.
Motorists are asked to avoid this area if possible, these roads will not be closed, however, there will be traffic delays.